CASE STUDY:
Global Warehousing & Storage


In 2023 we delivered our largest temporary warehouses to date, which equates to a combined 4,900 sqm of floor space. This is a part our client’s major business expansion plans, which Mar-key Group are proud to be a part of.

Besides a busy port in Humberside, the temporary warehouse facilities had to be secure but not fully-insulated. Furthermore, they needed it fast.

We helped them to obtain planning permission quickly to begin putting them in place.

We were required to build on their existing foundations without disruption to their ongoing operations.

Following a site visit, we discovered the need for a ground sealant to fix the structure.

Project


This full build project consisted of:

  • 2 off 35m x 65m on 6m leg clear span aluminium structures
  • Insulated steel sandwich panel wall cladding in 40mm trapezoidal finish (pigeon grey)
  • Thermo blow up PVC roof with white translucent external face with sunblock internal layer
  • Electrically-operated roller shutter doors.

“It’s as good as all of our longstanding warehouses and I think we’ll continue down this route with Mar-Key.”

– Simon Williams, Operations Director of Global Warehousing & Storage Ltd.

Final result


We delivered this project to their tight schedule and in coordination with their exact design requirements.

The two structures are joined together to achieve an impressive 70m span and 45,000sqm of floorspace. In order to cope with water runoff from both structures, we fitted a valley gutter in between.

We have enjoyed every moment of working with this client, who we only engaged with in early November! We signed off the project on time three weeks later.

Find out more about our temporary and semi-permanent warehousing solutions using the button below.

semi permanent warehouse space
semi permanent warehouse facilities
Port of Immingham warehouse space
temporary buildings
temporary warehouse space
port warehouses
temporary warehouses by port